July 7th,2021 The construction of Brazil 230kV transmission line Amazon River crossing project undertaken by China National Cable Engineering Corporation(hereinafter referred to as CCC) under China CACS Engineering Corporation has officially started.
The project is the second large crossing project across the Amazon River undertaken by CCC, including the design, supply and construction of 230kV double circuit and single conductor transmission line. The total length of the crossing section is 3556m and the height of the crossing tower is 253.5m. After the completion of the project, it will play a positive role in promoting the energy security of urban economic development in Brazil and contribute to the development of Brazil.